Question: Formulate a realistic Schedule Baseline for a project to build a software program to monitor cameras on stoplight across Jamaica. Use a Gantt chart and

Formulate a realistic Schedule Baseline for a project to build a software program to monitor cameras on stoplight across Jamaica. Use a Gantt chart and a schedule baseline chart to show the activity/schedule management plan. Duration of the project is 24 weeks.

example below of a schedule baseline for a different project as a guide

Schedule Baseline

Task Duration Start Date End Date
Project Management 16 days May 15, 2023 May 31, 2023
Completion & signing of Project Charter 5 May 15, 2023 May 20, 2023
Formation of Project team 3 May 21, 2023 May 24, 2023
Creation of Project Management Plan 3 May 25, 2023 May 28, 2023
Arrange meetings with Project Sponsor and Stakeholders 2 May 29, 2023 May 31, 2023
Land Preparation 16 days May 30, 2023 June 15, 2023
Design of Park Beautification 4 May 30, 2023 June 03, 2023
Approval of Layout Design of Park Beautification by sponsor 1 June 03, 2023 June 04, 2023
Approval of Layout Design of Park Beautification by Portmore Municipal Council 2 June 05, 2023 June 07, 2023
Permit granted by NEPA 3 June 08, 2023 June 11, 2023
Project approved 1 June 11, 2023 June 12, 2023
Clear Land 3 June 12, 2023 June 15, 2023
Procurement 15 days May 20, 2023 June 04, 2023
Prepare RFT 1 May 20, 2023 May 21, 2023
Advertise RFT 3 May 21, 2023 May 24, 2023
Evaluate bids (suppliers) 2 May 24, 2023 May 26,2023
Select supplier 1 May 26, 2023 May 27, 2023
Enter into contract supplier 3 May 27, 2023 May 30, 2023
Purchase of Equipment 3 May 31, 2023 June 03, 2023
Purchase of Materials and Resources 4 May 31, 2023 June 04, 2023
Purchase of Plants (trees, flowers, grass seeds and sod) 3 June 01, 2023 June 04, 2023
Purchase of Topsoil 1 June 03, 2023 June 04, 2023
Landscaping 147 days June 06, 2023 Oct 31, 2023
Measure and Dig Holes for Plants 14 June 06, 2023 June 20, 2023
Plant Trees (large) 17 June 06, 2023 June 23, 2023
Plant Trees (small) 28 June 24, 2023 July 22, 2023
Flowers Plant 27 July 22, 2023 Aug 18, 2023
Prep Land Space for Lawn Grass 13 Aug 18, 2023 Aug 31, 2023
Layout lawn grass (sod) 2 Aug 31, 2023 Sep 02, 2023
Add decorative stones around tress 14 Sep 02, 2023 Sep 14, 2023
Add mulch around trees and flowers 14 Sep 14, 2023 Sep 28, 2023
Final trim and cut of edges 21 Sep 28, 2023 Oct 19, 2023
Clear park of debris 5 Oct 19, 2023 Oct 24, 2024
Approval and sign off by Sponsor 2 Oct 25, 2023 Oct 27, 2023
Project Complete 0 Oct 28, 2023 Oct 28, 2023

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!