Question: Forward scheduling is: Select one: 1. start at today s date and schedule forward to determine the earliest date the job can be finished. If
Forward scheduling is:
Select one:
1. start at today s date and schedule forward to determine the earliest date the job can be finished. If each item takes one period to complete, the clipboards can be finished in three periods
2. Multiplying demand by two and holding materials on-site
3. Sending bills to customers and waiting for them to return payment
4. Starting at the due date and scheduling backwards to determine when to begin work