Question: Four Jobs must be processed through a single workcentre. The following table gives the processing times and due dates of the jobs: Processing Due Date

Four Jobs must be processed through a single workcentre. The following table gives the processing times and due dates of the jobs: Processing Due Date Job Time (in Days) A 5 10 4 6 6 Using the Critical Ratio Rule, in which order should the jobs be scheduled