Question: Four products (1, 2, 3, and 4) must be processed on one of four machines (A, B, C, and D). The times required in minutes

Four products (1, 2, 3, and 4) must be processed on one of four machines (A, B, C, and D). The times required in minutes for each product on each machine are shown below.

Machine

Product

A

B

C

D

1

10

9

16

12

2

8

14

17

5

3

19

20

11

7

4

8

18

5

10

The minimum time required to complete all the products is

Select one:

A. 29 minutes.

B. 36 minutes.

C. 27 minutes.

D. 33 minutes.