Question: Four trucks, 1 , 2 , 3 , and 4 are waiting on a loading dock at ABC Company that has only a single service
Four trucks, and are waiting on a loading dock at ABC Company that has only a single service bay. The trucks are labeled in the order that they arrived at the dock. Assume the current time is : PM The times required to unload each truck and the times that the goods they contain are due in the plant are given in the following table.
TruckUnloading Time minuteTime Material is Due: PM: PM: PM: PM
Using the shortest processing time SPT rule, determine the schedule and complete the following:
Instruction: Enter all your answer with decimal places, unless otherwise noted. Four trucks, and are waiting on a loading dock at ABC Company that has only a single service bay. The trucks are labeled in the order that they arrived at the dock. Assume the current time is : PM The times required to unload each truck and the times that the goods they contain are due in the plant are given in the following table.
Using the shortest processing time SPT rule, determine the schedule and complete the following:
Instruction: Enter all your answer with decimal places, unless otherwise noted.
The mean flow time is
The average tardiness is
The number of tardy trucks is
The flow time for Truck is
The first truck to be unload is Truck No integer
The last truck to be unloaded is Truck No integer
minutes.
minutes.
Enter
Enter
The completion time for Truck is
PMEnter as
mathrmX: mathrmXX use hour format
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock