Question: FPIF QUESTION Project Completed UNDER Target Cost Using what we learned in class for FPIF and given the data below, what is the buyer payout

FPIF QUESTION
Project Completed UNDER Target Cost
Using what we learned in class for FPIF and given the data below, what is the buyer payout to the seller?
, Target Cost $1,000K
, Target Fee (Sellers Profit) $100K
, Target Price $1,100K
Ceiling Price $1,200K(The maximum pay-out to the seller)
Share Ratio 70/30
Actual Cost $800K
CPIF QUESTION Project Completed UNDER Target Cost
Using what we learned in class for CPIF and given the data below, what is the buyer payout to the seller?
, Target Cost $1,000K
, Target Fee (Sellers Profit) $100K
, Target Price $1,100K
, Ceiling Price $1,200K(The maximum pay-out to the seller)
Share Ratio 8515(buyer absorbs 85% of the risk and the seller absorbs 15% of the risk)
Actual Cost $800K
 FPIF QUESTION Project Completed UNDER Target Cost Using what we learned

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!