Question: Freedom Corp. has provided the following data from its activity-based costing system: Activity Cost Pool Total Cost Total Activity Designing products $1,200,000 7,900 product design
Freedom Corp. has provided the following data from its activity-based costing system:
Activity Cost Pool Total Cost Total Activity
Designing products $1,200,000 7,900 product design hours
Setting up batches $35,000 700 batch set-ups
Assembling products $100,000 6,500 assembly hours
What is the activity rate for the designing products cost-pool?
(A) $77.70 (B) $151.90(C) $17.10 (D) $143.22
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts