Question: French: Si la prime de risque du march et le taux sans risque sont, respectivement, de 10% et 3 %, quel est le cot du
French: Si la prime de risque du march et le taux sans risque sont, respectivement, de 10% et 3 %, quel est le cot du capital dun projet dont le bta est de 0,75 ?
English:
If the market risk premium and the risk-free rate are 10% and 3%, respectively, what is the cost of capital for a project with a beta of 0.75?