Question: fRequired [round to 2 decimal places}: Using the high low method, calculate the fixed cost component of overhead and the variable rate per kWh. Estimate


\fRequired [round to 2 decimal places}: Using the high low method, calculate the fixed cost component of overhead and the variable rate per kWh. Estimate the expected cost for overhead in September assuming that 13,100 kwh's of power are used in the month. 3. Give one smic exomp."_e of a cost that might be included in the variable cost 1you calculated above
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts