Question: From Subcontractor standpoint: When the contractor was bidding out the MEP subcontract, they knew that the market was tough and subs were more desperate for
From Subcontractor standpoint:
When the contractor was bidding out the MEP subcontract, they knew that the market was tough and subs were more desperate for work. The contractor added clauses for no-damage-for-delay, pay-when-paid, and waiving of lien rights into the subcontract.
Question Below
- Explain whether the owner would have those same clauses in the contract with the prime contractor. What are the ethical implications for the contractor to insist on these clauses in their contracts with their subs?
- What are a subcontractors options in dealing with a contract that includes such exculpatory clauses?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
