From the activity cost schedule, determine the non-value-added costs. quality control activities activity cost audit process $50,000
Fantastic news! We've Found the answer you've been seeking!
Question:
From the activity cost schedule, determine the non-value-added costs.
quality control activities | activity cost |
audit process | $50,000 |
Training of machine operators. | 28,000 |
Processing of returned products | 19,000 |
Scrap processing (disposal) | 25,000 |
Redo | 8,000 |
Preventive Maintenance | 30,000 |
product design | 46,000 |
warranty work | 12,000 |
finished product inspection | 23,000 |
Related Book For
Auditing and Assurance services an integrated approach
ISBN: 978-0132575959
14th Edition
Authors: Alvin a. arens, Randal j. elder, Mark s. Beasley
Posted Date: