Question: From the data shown below, calculate the earned value of each control account as of 5/30/19. Assume all control account work is on schedule except

From the data shown below, calculate the earned value of each control account as of 5/30/19. Assume all control account work is on schedule except as noted below.

Control Account

Scheduled Start

Scheduled Completion

Budgeted Value

EV Progress Rule

1

3/3/2019

6/30/2019

10,000

Percent Complete with Gates (Note 1)

2

5/5/2019

6/6/2019

3,000

Fixed Formula: 50/50

3

5/26/2019

6/6/2019

1,000

Fixed Formula: 0/100

4

5/12/2019

5/30/2019

2,000

Fixed Formula: 30/70

5

4/14/2019

7/11/2019

15,000

Weighted Milestones (Note 2)

Note (1): Five equally-valued gates have been established in this control account. Two of the five gates are complete as of 5/30/19. The Control Account Manager estimates that half of the work required for the third gate has also been completed.

Note 2: Six milestones have been established in this control account with the following values: (1) milestone 1 20%; milestone 2- 15%; milestone 3 10%; milestone 4 25%; milestone 5 - 15%; milestone 6 15%. Three of the milestones are complete as of 5/30/19.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!