Question: From the figures given below, calculate Economic Order Quantity ( EOQ ) and Total cost at EOQ? Total consumption of material per year 1 0

From the figures given below, calculate Economic Order Quantity (EOQ) and Total cost at EOQ? Total consumption of material per year 10,000 kgs Buying cost per order $ 50 Unit cost of material $2 per kg Carrying and storage cost 8%

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts