From the following data, Calculate a) Material Cost Variance b) Material Price Variance c) Material Usage Variance. Materials X Y Z Standard Quantity Kg. 8,000 3,000 2,000 Standard Price Actual Quantity Kg. 7,500 3,300 2,400 Rs. 1.05 2.15 3.30 Actual Price Rs. 1.20 2.30 3.50 From the following data, Calculate a) Material Cost Variance b) Material Price Variance c) Material Usage Variance. Materials X Y Z Standard Quantity Kg. 8,000 3,000 2,000 Standard Price Actual Quantity Kg. 7,500 3,300 2,400 Rs. 1.05 2.15 3.30 Actual Price Rs. 1.20 2.30 3.50
Expert Answer:
Answer rating: 100% (QA)
a Material Cost Variance Material Cost Variance Standard Quantity Standard Price Actual Quanti... View the full answer
Related Book For
Management Accounting
ISBN: 9780077185534
6th Edition
Authors: Will Seal, Carsten Rohde, Ray Garrison, Eric Noreen
Posted Date:
Students also viewed these accounting questions
-
What does the current ratio tell us about the organization? What does the days cash on hand tell us about the organization? Current Assets Current Ratios for 2022 to 2024 Current Liabilities 2024...
-
The article "Estimating Resource Requirements at Conceptual Design Stage Using Neural Networks" (A. Elazouni, I. Nosair, et al., Journal of Computing in Civil Engineering, 1997:217-223) suggests that...
-
The following additional information is available for the Dr. Ivan and Irene Incisor family from Chapters 1-5. Ivan's grandfather died and left a portfolio of municipal bonds. In 2012, they pay Ivan...
-
A construction company is considering taking on a new project. The total project cost is $5 million, and there is a 70% chance that the project will be completed on time and within budget, resulting...
-
Emil Family Importers sold goods to Acme Decorators for $20,000 on November 1, 2014, accepting Acme's $20,000, six-month, 6% note. (a) Prepare Emils; November 1 entry, December 31 annual adjusting...
-
An engine receives 660 J of heat from a hot reservoir and gives off 420 J of heat to a cold reservoir. What are (a) The work done (b) The efficiency of this engine?
-
If, as evidenced by statements from the Presidents Task Force and the FBI director, implicit biases are problematic in law enforcement, can screening techniques be developed to eliminate candidates...
-
Quoton Corporation acquired 80 percent of Tempro Companys common stock on December 31, 20X5, at underlying book value. The book values and fair values of Tempros assets and liabilities were equal,...
-
Required information [ The following information applies to the questions displayed below ] Now that operations for outdoor clinics and TEAM events are running smoothly, Suzie thinks of another area...
-
A heat engine running backward is called a refrigerator if its purpose is to extract heat from a cold reservoir. The same engine running backward is called a heat pump if its purpose is to exhaust...
-
Required information (The following information applies to the questions displayed below.) During the current year, Ron and Anne sold the following assets: (Use the dividends and capital gains tax...
-
The Penguin Textile Company sells shirts for men and boys. Results for January 2 0 2 3 are summarized below. Men's Boy's Total Revenue $ 1 7 2 , 8 0 0 $ 7 2 , 0 0 0 $ 2 4 4 , 8 0 0 Variable costs 1 2...
-
SINGLE, MARRIED FILING SEPERATELY, OR HEAD OF HOUSEHOLD SINGLE, MARRIED FILING SEPERATELY, OR HEAD OF HOUSEHOLD Over $0 $12,500 $50,000 But Not Over $12,500 $50,000 Tax Due Is 4% of taxable income...
-
17. S T D -3 -2 graph of glx) 2 The graph of the continuous function g is shown above for -46x4. The Function g is twice differentiable, except at x=0. let & be the function with flo1=-2 and f'(x) =...
-
Tim works for HydroTech, a manufacturer of high-pressure industrial water pumps. He reports directly to the CFO, and she has asked him to calculate HydroTech's WACC. He has gathered the following...
-
You are appraising a 15,450 square foot (SF) building and using the Cost Approach. The base cost is $50/SF, the local multiplier is 1.05, the current cost multiplier is 0.92. The land value is...
-
Find the EAR in each of the following cases (Use 365 days a year. Do not round intermediate calculations. Enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.): Effective Rate...
-
Find the equation of the plane passing through the points P 5,4,3 ,Q 4,3,1 and R 1,5,4
-
Shimada Products Corporation of Japan is anxious to enter the electronic calculator market. Management believes that in order to be competitive in world markets, the price of the electronic...
-
Matheson Electronics has just developed a new electronic device which, when mounted on an automobile, will tell the driver how many miles the automobile is traveling per gallon of gasoline. The...
-
The repair shop of Quality Motor Company uses standards to control the labour time and labour cost in the shop. The standard labour cost for a motor tune-up is given below: The record showing the...
-
Given the following project (all times are in days): LO6 Act- Prede- Normal Normal Crash Crash ivity cessor Time Cost Time Cost a 5 $50 3 $150 b 4 40 2 200 c b 7 70 6 160 d a, c 2 20 1 50 e a, c 3...
-
Given the project shown in Figure 5-10 of Chapter 5, assume that a facility used by activities c and d is scarce. To which activity would you assign the facility first, given the following rules: LO6...
-
Given the following project to landscape a new building site: Activity LO6 Immediate Duration Resource Activity Predecessor (days) Used A 2 X, Y B A 2X C A 3X D B, C 4 X, Y E D 3 W, X F D 1 W, X, Y...
![Mobile App Logo](https://dsd5zvtm8ll6.cloudfront.net/includes/images/mobile/finalLogo.png)
Study smarter with the SolutionInn App