Question: From the given shovels: 1 8 , 2 0 , 2 5 , 4 5 and 6 0 m 3 bucket capacity, select the appropriate

From the given shovels: 18,20,25,45 and 60m3 bucket capacity, select
the appropriate one for a bauxite mine using shovel-truck production
equipment. The production data are: required production in bank: 15,000
tons/shift; shift operating time: 7 hr ; availability of the shovel: 50minhr.
muck: medium digging; cycle time 34 sec ; bank density: 2.0 tons/yd3;
loose density: 1.30 tons/yd3; swing angle: 120.