Question: From the information in the chart below, draw a project network with Early Start, Late Start, Duration, Early Finish and Late finish included. Also, report

From the information in the chart below, draw a project network with Early Start, Late Start, Duration, Early Finish and Late finish included. Also, report the critical path and project duration.
From the information in the chart below, draw a
You were assigned as manager of the following project: QMPORTANT: Use the following heuristics: minimum slack, smallest duration, lowest ID number. No splitting of activities is possible