Question: From the network shown below, construct the precedence table. What is the shortest time for completion of the task? A(5) D(4) B(1) F(3) C(3)
From the network shown below, construct the precedence table. What is the shortest time for completion of the task? A(5) D(4) B(1) F(3) C(3) E(2) G(1) The shortest time for completion of the task is weeks.