Question: From the sampling information provided below, determine the projected error for each scenario independently and conclude on the impact to materiality if performance materiality is

From the sampling information provided below, determine the projected error for each scenario independently and conclude on the impact to materiality if performance materiality is set at $6,500. (Round answers to 0 decimal places, e.g. 5,275. Enter negative amounts usingr either a negative sign preceding the number e.g. -45 or parentheses e.g. {45).} Scenario Error Sample Population Projected Error Impact 1 $[3,244} $43,100 $64,960 $ v 2 $4,500 $11,000 $19,000 $ v 3 $2,721 $20,563 $52,456 $ v Save for Later Attempts: 0 of 1 used