Question: Ft Moore, GA - PMP Exam Prep PMP Baseline Test Question 2 1 of 2 5 1 Point On a project to create a new
Ft Moore, GA PMP Exam Prep
PMP Baseline Test
Question of
Point
On a project to create a new public website for a large car dealer, the general manager of the dealership tells you that he hopes your team can get at least a basic version of the website set up within a month to meet the new car sales department needs, and then add in needed webpages later for the service department, parts department, and finally the used car sales department, in that order. What project approach would be best?
Select the correct response:
The Critical Path Method is called for since we know the order in which each feature of the website must be delivered
The Work Breakdown Structure approach would be best to fully define each department's requirements and deliverables
Agile methods would be best because this project will need to combine incremental delivery of website features with iterative feedback from each department regarding how their web pages should interface with the already live website pages
Predictive methods would work best since the general manager has clearly laid out the delivery requirements
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock