Question: Ft Moore, GA - PMP Exam Prep Question 2 0 of 2 5 What does the numbering system on a work package indicate? Select the
Ft Moore, GA PMP Exam Prep
Question of
What does the numbering system on a work package indicate?
Select the correct response:
The estimated cost for the work
To whom it is assigned
The estimated duration of the work
To which node on the WBS the work package belongs
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
