Question: Fun Vehicles, Inc. makes beach buggies on an assembly line. The total productive time to make one buggy is 300 seconds. The current line has

 Fun Vehicles, Inc. makes beach buggies on an assembly line. The

Fun Vehicles, Inc. makes beach buggies on an assembly line. The total productive time to make one buggy is 300 seconds. The current line has a 90-second cycle time and consists of four workstations. The balance delay of this line must be: A) greater than 0% but less than 6%. B) greater than 6% but less than 12%. C) 0% D) greater than 12% but less than 18%