Question: Funds that are for identified risks that have a low probability of occurring and that decrease as the project progresses are called _ _ _

Funds that are for identified risks that have a low probability of occurring and that decrease as the project progresses are called ______ reserves.
Group of answer choices
management
padded
contingency
unidentified risk