Question: further calculations. ) table [ [ Performance , Observation ( seconds ) , ] , [ Element , Rating, 1 , 2 , 3
further calculations.
tablePerformanceObservation secondsElementRating,Grasp and place bag,Fill bag,Seal bag,Place bag on conveyor,
Bag breaks open; included as delay in the allowance factor
Conveyor jams; included as delay in the allowance factor
a The standard time for this process seconds round your response to two decimal places