Question: Further to the data provided above for 3 estimates, the management is now contemplating crashing the network to the minimum possible time under the crash

Further to the data provided above for 3 estimates, the management is now contemplating crashing the network to the minimum possible time under the crash cost schedule provided below. (a) What would be the minimum duration of the project? and (b) what is the corresponding crash cost? (c) If the management wishes to crash the project down to 29.85 weeks only, what will be the total cost incurred and corresponding crash schedule? You must submit computer outputs (original) for questions #5 and #6 to earn credits.
Activity Normal Time in weeks* Crash time in weeks Normal Cost ($)** Crash Cost ($)** A 7.11761000011500
B 3.05280009000
C 2.51500016000
D 472507895 E 5.5750010000 F 3.580009000 G 1.9510001250 H 3.555005800 I 31000015000 J 820005000 K 0.170008000 L 0.580009000 M 7.560009000 N 5.550007000 O 560008000 P 1860009000 Q 3.580009000 R 2.560008000 S 2.5900010000 T 380008200 U 570008000 V 650005600 W 3.580009500 X 71000015000 Y 5.5500010000 Z 5.560008000
*Populate this column from your calculation from question #5. For example the entry corresponding to activity A =(a +4m + b)/6=(5.6+(4 x 7)+9.1)/6=7.117 weeks (Rounded to three decimal points); Activity B similarly is 3.05 weeks.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!