Question: Gantt Charting The table below includes information about four jobs and three work centers. Assume that six hours is required to transfer a job from
Gantt Charting The table below includes information about four jobs and three work centers. Assume that six hours is required to transfer a job from one work center to another (move time not including waiting time for busy machines). Sequence the jobs with a Gantt chart. Use the following priority order: 1, 2, 3, 4. Can you tell if any jobs will be late? Which ones? Can a simple reordering of job priorities alleviate the problem?
Job | Work center / Machine hours | Due date (days) |
1 | A/2, B/1, C/4 | 3 |
2 | C/4, A/2 | 2 |
3 | B/4, A/2 | 2 |
4 | B/4, A/2, C/3 | 3 |