Question: gathering cost data from the first three units, which Nebula produced under a research and development contract, she found that the first unit took 2

gathering cost data from the first three units, which Nebula produced under a research and development contract, she found that the first unit took 2,000 labor hours, the second took 1,800 labor hours, and the third took 1,692 hours. Use .Exhibit 6.5.
In a contract for three more units, how many labor hours should Khatri plan for?
Note: Round your answer to the nearest whole number.