Question: gathering cost data from the first three units, which Nebula produced under a research and development contract, she found that the first unit took 2
gathering cost data from the first three units, which Nebula produced under a research and development contract, she found that the first unit took labor hours, the second took labor hours, and the third took hours. Use Exhibit
In a contract for three more units, how many labor hours should Khatri plan for?
Note: Round your answer to the nearest whole number.