Question: Gaucher Corporation has provided the following data from its activity-based costing accounting system: Activities Estimated Overhead Cost Expected Activity Designing products $582,016 4,547 product design
Gaucher Corporation has provided the following data from its activity-based costing accounting system:
Activities Estimated Overhead Cost Expected Activity
Designing products $582,016 4,547 product design hours
Setting up batches $29,670 960 batch set-ups
Assembling products $19,440 1,620 assembly hours
The Activity rate for the "designing products" activity cost pool is closest to:
Please show the steps