Question: Gelos Enterprises Implement new Employee records system Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Identification of stakeholders Implementation
Gelos Enterprises Implement new Employee records system Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Identification of stakeholders Implementation Strategy - consult and plan with stakeholders Stakeholders - roles, accountabilities Communicate changes to staff Contingency plan - create Follow work plans, schedules - system now begin to implement Communication follow up (email, meetings etc) follow up with management Adapting plans and schedules to meet work needs and conflicting priorities Achievement of task goals - check progress Monitor the use of the system - Testing the new system Develop strategy to train new and existing employees Conduct training needs analysis Establish training plan - create training session schedule, training content etc. (PowerPoint presentation; organise activities; handouts etc) Deliver training Supervise staff using the new system Seek feedback from others Evaluate new system - discuss with management Implement further changes Completion / end dates
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts