Question: geotechnical engineer in charge at a specific site has decided to use an anchored sheet pile wall system penetrating clayey soil ( next page )
geotechnical engineer in charge at a specific site has decided to use an anchored sheet pile wall system penetrating clayey soil next page The anchor tie rod is located at point O and will be contributing with a force F against the lateral pressure from the backfill.
The lateral pressure distribution diagram above the dredge line is identical to that of cantilever sheet pile wall penetrating clay as shown in your class note However, the net pressure distribution diagram below the dredge line is simpler, since the theoretical depth of penetration of the sheet pile will be considerably reduced due to the addition of an anchor tie rod.
For a given set of soil properties and sheet pile dimensions, as shown below:
Determine the actual depth of embedment D using a increase of theoretical depth of embedment as factor of safety FOS
Determine the magnitude of the anchor force F using the actual depth of embedment D obtained in part A
Soil
Y
Ysat
Sand
KNm
KNm
Clay
KNm
KNm
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock