Question: Get the answer in less than an hour and get a high rating 2.3The following data are from the costing records of John Ltd. In
Get the answer in less than an hour and get a high rating

2.3The following data are from the costing records of John Ltd. In respect of job No. 150: Materials used BD. 5000 Direct Wages: Department A - 60 hours at BD 8 per hour Department B - 100 hours at BD 5 per hour Department C - 50 hours at BD 6 per hour Overhead for these three departments were estimated as follows: Variable overheads: Department A - BD 60000 for 3000 Direct labour hours Department B - BD 20000 for 2000 Direct labour hours Department c - BD 80000 for 2000 Direct labour hours Fixed overheads: BD 10 per working hour You are required to calculate the cost of job number 150 and calculate the price for the job to give a profit of 25% on total cost.cz Particulars BD BD Selling price Show your calculations here