Question: Getting formal sign - off for a project from a sponsor can almost be impossible at some companies. How is formal acceptance and closure of
Getting formal signoff for a project from a sponsor can almost be impossible at some companies. How is formal acceptance and closure of a contract described in the PMBOK?
Any of the following.
The signature of the primary stakeholder.
The person or organization responsible for contract administration should provide the seller with verbal notice that the contract has been completed.
The person or organization responsible for contract administration should provide the seller with formal written notice that the contract has been completed.