Question: Gilsbrad Corp. is evaluating a project using scenario analysis. The project will have a 30% chance of generating a NPV of $154,000, a 40% chance
Gilsbrad Corp. is evaluating a project using scenario analysis. The project will have a 30% chance of generating a NPV of $154,000, a 40% chance of generating a NPV of $46,000, and a 30% chance of generating a NPV of -$24,000. What is the project's standard deviation on its expected NPV? Submit your final answer rounded to two decimal places (Ex. $0.00)