Question: Give complete solution with Activity on arrow diagram Q. 6: (10 marks) If'depends stands for greater than andcontrols represents less or smaller than, draw the

Give complete solution with Activity on arrow diagram
Q. 6: (10 marks) If'depends" stands for greater than and"controls" represents less or smaller than, draw the Network diagram for the following problem: Estimated times (in weeks) for the jobs of a project are given below: A(13),B(5),C(8),D(10),E(9),F(7),G(7),H(12),I(8),J(9),K(4),L(17). The constraints governing the jobs are as follows: A and B start jobs; A controls C,D and E;B controls F and J;G depends upon C;H depends on D; E and F controls I and L;K follows J;L is also controlled by K;G,H,I and L are the last jobs. Find critical path and the project duration