Question: Given: 9 activities - 1-3 take lomin / unit each, 4-5 takes 5 min/unit each 3 Resources - 2 are employees, I'd is equipment Sam

 Given: 9 activities - 1-3 take lomin / unit each, 4-5

Given: 9 activities - 1-3 take lomin / unit each, 4-5 takes 5 min/unit each 3 Resources - 2 are employees, I'd is equipment Sam - responsible for activities 1-3, works 40 hrs / week Emily - responsible for " 4-6, 40 his/ week work Machine - " . 7- 9, " to his/ week 3 Jobs - A, B, C Activities Required! A B C 4, 8, 9 1 , 2 , 3 , 5 , 6 , 7 , 2 2, 3 , 4, 5, 6 , 7, 8, 9 Weekly demands and Profit margins A - So units / week - $20 / unit profit B - loo units / week - $75/ unit ( - 60 units / week - $60 / unit profit