Question: Given a project with the following activities Activity Immediate Predecessor likelyde 13 Pessimistic time (day) 11 A IwOnIDI optimistic Mast time time (day) 5 8

Given a project with the following activities

Given a project with the following activities Activity Immediate Predecessor likelyde 13 Pessimistic time (day) 11 A IwOnIDI optimistic Mast time time (day) 5 8 8 6 8 9 12 5 6 5 6 2 3 4 4 5 7 15 9 7 G H I 8 Determine @ the prob. of finishing the project by day 24 The probability of finishing the project by day 21