Question: Given a project with the following characteristics, answer the following questions: You are the project manager of a project to build fancy birdhouses. You are
Given a project with the following characteristics, answer the following questions:
You are the project manager of a project to build fancy birdhouses.
You are to build two birdhouses a month for months.
Each birdhouse is planned to cost $
Your project is scheduled to last for months.
It is the beginning of month
You have built birdhouses and your CPI is
What is the projects TCPI using the projects budget at completion?
A
B
C
D
Senior management wants to the percentage of the project that is complete. What should you report?
A
B
C
D
Imagine if instead of months and costing $ the project was in month three and costing $ What formula might you use for BAC?
ABAC EVCPI SPI AC
B new bottomup estimate
C AC new ETC
D AC BAC EV
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock