Question: Given an activity's optimistic, most likely, and pessimistic time estimates of 3 , 5 , and 1 5 days respectively compute pert standard deviation for

Given an activity's optimistic, most likely, and pessimistic time estimates of
3,5, and 15
days respectively compute pert standard deviation for the activity