Question: Given below is an excerpt from a management performance report: Budget Actual Difference Contribution margin $900000 $970000 $70000 Controllable fixed costs $700000 $630000 $70000 The
Given below is an excerpt from a management performance report:
| Budget | Actual | Difference | |
| Contribution margin | $900000 | $970000 | $70000 |
| Controllable fixed costs | $700000 | $630000 | $70000 |
The managers overall performance
|
| is 70% above expectations. |
|
| is equal to expectations. |
|
| cannot be determined from information given. |
|
| is 70% below expectations. |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts