Question: Given below is the time-cost trade-off data for a small project. Assume the Indirect Cost is SR100/day. Calculate the optimal project duration. Activity Predecessors

Given below is the time-cost trade-off data for a small project. Assume the Indirect Cost is SR100/day. Calculate the optimal project duration. Activity Predecessors Normal Crash Duration D. Cost Duration D. Cost w. days Slope SR w. days SR 4 100 300 100 B 3 200 200 , 2. 50 100 50 D , 3. 100 2. 300 200 4 150 400 83.3 F , D 4. 250 400 50 G D, E 300 00 \00 H. F, G 3. 200 300
Step by Step Solution
3.43 Rating (159 Votes )
There are 3 Steps involved in it
1 STEP1 NORMAL DURATION DURATION 23 DAYS 2 STEP2 CRASH DURATION 3 OPTIMAL DURATION 4 STEP4 SUMMARY ... View full answer