Question: Given Data Table Activity Predecessor Pessimistic (a) Likely Optimistic (m) (b) A None I 24 10 8 BA 1575 C A 2 3 10 w

Given Data Table Activity Predecessor Pessimistic
Given Data Table Activity Predecessor Pessimistic (a) Likely Optimistic (m) (b) A None I 24 10 8 BA 1575 C A 2 3 10 w w I T = 19 25 3 E I B [ TC G C HIEF D.G HI + 16 CD 7 1. Determine the expected duration from the equation Duration - (a + 4m + b)/6 (10 points) 2. Construct the diagram (activity on node) (you may draw it in paper and submit a picture of it) (30points) 3. Determine the critical path ( 10 points)