Question: Given: Excavation Volume = 1 5 0 cu . m . using 8 helpers assigned in manual digging Gravel Bedding = 4 0 cu .

Given:
Excavation Volume =150 cu.m. using 8 helpers assigned in manual digging
Gravel Bedding =40 cu.m. using 8 helpers assigned in manual backfilling
Rebar Footing & 1st Lift Column =5,255 kgs using 4 skilled workers assigned in fabrication and 4 skilled workers assigned in installation
Formworks for 1st Lift Column =58 sq.m. using 1 skilled worker +1 helper for installation, using 1 skilled worker +1 helper for fabrication
Forming and Shoring of 1st Lift Column =58 sq.m. using 1 skilled worker +1 helper for forming and shoring
Concrete Pouring for footing and column =35 cu.m. using 3 helpers assigned in mixing machine, and 2 skilled workers +4 helpers assigned in concrete pouring
Stripping of Forms =58 sq.m. using 2 skilled workers and 2 helpers
Backfilling Volume =188 cu.m. using 8 helpers assigned in manual backfilling
Helper's Rate = Php 598.00 per day
Skilled Worker's Rate = Php 750.00 per day
Overhead =20%
DETERMINE the TOTAL LABOR COST for SUBSTRUCTURE using the Philippines Manpower Productivity Ratio
Given: Excavation Volume = 1 5 0 cu . m . using 8

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!