Question: Given : Instrution Type 1, 2, and 3 on Machine M CPI 1 = 1.3 ; CPI 2 = 1.7; CPI 3 = 2.2 a)
Given : Instrution Type 1, 2, and 3 on Machine M
CPI1 = 1.3 ; CPI2 = 1.7; CPI3 = 2.2
a) What is Average CPI of machine M running a program P that has 29% Type 1 instructions, 31% Type 2 instructions, and the remainder Type 3 instructions?
b) What is the TOTAL number of cycles required to run P to completion if Ps instruction count IC = 3395 ?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts