Question: Given part b, answer parts c and d. Make sure to answer both charts in the bortom 2 photos. Kelle Carpet and Trim installs carpet


Kelle Carpet and Trim installs carpet in commercial offices. Peter Kelle has been very concerned with the amount of time it took to complete several recent jobs Some of his workers are very unreliable. A list of activities and their optimistic completion time, the most likely completion time, and the pessimistic completion time (ail in days) for a new contract are given in the following table This exercise contains only parts b,c, and d b) Activities on the critical path for the project are B-E. G-1 - K The total project completion time is 413d days (Round your response to two decimal places) For the given project, the Latest start (LS) and latest finish (LF) are: (Aound your responses to huo decimal places.) d) Reterring to the he probability that Kelle Carpet and Trim will finish the project in 42 days or less is Enter as a probability and round your response to two decimal places.) c) For the given project, the earliest start (ES) and earliest finish (EF) are (Round your responses to two decimal places.)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts