Question: Given that A may not be an exact activity time and if A has a pessimistic time of 6 to complete, an optimistic time of
Given that A may not be an exact activity time and if A has a pessimistic time of 6 to complete, an optimistic time of 3 to complete, and a most likely time of 5 to complete, the expected time to complete A is _______.
Group of answer choices
4.83
3.97
5
5.66
Step by Step Solution
There are 3 Steps involved in it