Question: Given that: Sawing = 7 units / hr Sanding = 5 units / hr Drilling = 2.5units / hr Welding = 2 units / hr
Given that:
Sawing = 7 units / hr
Sanding = 5 units / hr
Drilling = 2.5units / hr
Welding = 2 units / hr
Assembly:
Asse 1 = 0.8 units / hr
Asse 2 = 0.8 units / hr
Asse 3 = 0.8 units / hr
a) is the bottleneck.
b) The bottleneck time is minutes per unit (round your response to two decimal places).
c) The throughput time of the overall system is nothing minutes (round your response to two decimal places).
d) If the firm operates 12 hours per day, 20 days per month, the monthly capacity of the manufacturing process is nothing units (enter your response as a whole number).