Question: Given that the AC = 5 0 0 , PV = 4 0 0 and EV = 3 0 0 , this project is currently
Given that the AC PV and EV this project is currently budget andschedule.Multiple Choiceon, onunder, ahead ofover, ahead ofunder, behindover, behind