Question: given that the engineering support work package has a level of effort EVM technique, what is the BCWP for the month of November? work package

given that the engineering support work package has a level of effort EVM technique, what is the BCWP for the month of November? work package 8 engineering support uses an LOE EVM technique with BCWS scheduled as follows: August $6983 ; September 8938; October 8938; November $9760; and December $8938. The BAC is 43,557. Time now is at end of November . The current BCWS for each month is; August $6983; September 8938; November $9760 and december $8938. The current BCWP for each month is blank