Question: Given the data below calculate and show formula the following; The expected project finish time. The variances for the applicable tasks. The total critical path
Given the data below calculate and show formula the following;
- The expected project finish time.
- The variances for the applicable tasks.
- The total critical path variance.
- The total critical path standard deviation.
The customer has seen the Technology Refresh (Version B) project schedule and the expected project finish time. However, the customer is concerned about the schedule risk of the project. Therefore, he wishes to know the following (i.e., determine the following):
- The probability of finishing the project in 287 days.
- The probability of finishing the project in 273 days.
| ID | Task | Optimistic Duration (days) | Most Likely Duration (days) | Pessimistic Duration (days) | PERT Expected Duration (days) | Critical Path | Variance | |
| 1 | TECHNOLOGY REFRESH (VERSION B) PROJECT | O | P | |||||
| 2 | Initiating | |||||||
| 3 | Meet with key stakeholders | 2 | 3 | 12 | 4 | |||
| 4 | Finalize statement of work | 2 | 10 | 15 | 10 | |||
| 5 | Secure project team leads | 2 | 2 | 4 | 2 | |||
| 6 | Finalize stakeholder register | 2 | 10 | 13 | 9 | |||
| 7 | Develop project charter | 2 | 5 | 17 | 7 | |||
| 8 | Finalize project charter | 2 | 4 | 8 | 4 | |||
| 9 | Planning | |||||||
| 10 | Scope Planning | |||||||
| 11 | Requirements | |||||||
| 12 | Develop/finalize functional requirements | 10 | 18 | 28 | 18 | |||
| 13 | Develop/finalize hardware requirements | 12 | 16 | 18 | 16 | |||
| 14 | Develop/finalize software requirements | 10 | 16 | 30 | 17 | |||
| 15 | Develop/finalize requirements traceability matrix | 11 | 14 | 28 | 16 | |||
| 16 | Finalize project deliverables | 2 | 2 | 3 | 2 | |||
| 17 | Develop scope statement | 4 | 9 | 10 | 8 | |||
| 18 | Finalize/Update WBS | 2 | 3 | 5 | 3 | |||
| 19 | Schedule (Time) and Cost Planning | |||||||
| 20 | Finalize hardware/software costs | 2 | 4 | 5 | 4 | |||
| 21 | Update activities and duration estimates | 6 | 12 | 14 | 11 | |||
| 22 | Human Resource Planning | |||||||
| 23 | Finalize resource requirements | 6 | 10 | 14 | 10 | |||
| 24 | Finalize project costs | 4 | 11 | 19 | 11 | |||
| 25 | Identify training requirements | 2 | 4 | 5 | 4 | |||
| 26 | Complete training activities | 6 | 12 | 14 | 11 | |||
| 27 | Quality Planning | |||||||
| 28 | Determine impacted quality processes | 2 | 3 | 4 | 3 | |||
| 29 | Finalize quality management plan | 2 | 10 | 18 | 10 | |||
| 30 | Risk Planning | |||||||
| 31 | Update project risks | 3 | 6 | 12 | 7 | |||
| 32 | Draft risk register | 2 | 3 | 8 | 4 | |||
| 33 | Finalize risk management plan | 2 | 4 | 7 | 4 | |||
| 34 | Finalize Project Plan | |||||||
| 35 | Finalize communications management plan | 2 | 3 | 4 | 3 | |||
| 36 | Finalize procurement management plan | 2 | 6 | 14 | 7 | |||
| 37 | Finalize stakeholder management plan | 2 | 2 | 5 | 3 | |||
| 38 | Finalize project schedule/cost baseline | 2 | 13 | 19 | 12 | |||
| 39 | Finalize project plan | 2 | 5 | 16 | 6 | |||
| 40 | Obtain approval for project plan | 2 | 4 | 7 | 4 | |||
| 41 | Executing | |||||||
| 42 | Hardware | |||||||
| 43 | Procure hardware from suppliers | 10 | 24 | 32 | 23 | |||
| 44 | Software | |||||||
| 45 | Obtain software OS licenses | 6 | 11 | 20 | 12 | |||
| 46 | Obtain software application licenses | 6 | 8 | 17 | 9 | |||
| 47 | Pilot Testing | |||||||
| 48 | Setup test area | 1 | 2 | 2 | 2 | |||
| 49 | Load software onto pilot machines | 4 | 6 | 8 | 6 | |||
| 50 | Validate functionality | 3 | 6 | 8 | 6 | |||
| 51 | Deployment | |||||||
| 52 | Configure production hardware | 10 | 25 | 33 | 24 | |||
| 53 | Deploy production hardware | 11 | 19 | 23 | 18 | |||
| 54 | Load software to deployed hardware | 12 | 17 | 19 | 17 | |||
| 55 | Testing | |||||||
| 56 | Validate startup on deployed hardware | 4 | 9 | 18 | 10 | |||
| 57 | Perform OS testing | 4 | 8 | 17 | 9 | |||
| 58 | Perform application testing | 4 | 19 | 28 | 18 | |||
| 59 | Obtain formal sign-off from users | 6 | 17 | 24 | 16 | |||
| 60 | Monitoring and Controlling | |||||||
| 61 | Formal Customer Review 1 | |||||||
| 62 | Hold formal customer review after project plan approval | 1 | 3 | 4 | 3 | |||
| 63 | Update project plan | 4 | 10 | 20 | 11 | |||
| 64 | Formal Customer Review 2 | |||||||
| 65 | Obtain updates regarding key deliverables from project team | 5 | 18 | 22 | 17 | |||
| 66 | Hold formal customer review after pilot testing | 5 | 7 | 11 | 7 | |||
| 67 | Update project plan | 4 | 8 | 15 | 9 | |||
| 68 | Closing | |||||||
| 69 | External | |||||||
| 70 | Finalize procurement with suppliers | 5 | 18 | 24 | 17 | |||
| 71 | Customer Approval | |||||||
| 72 | Hold final customer review | 1 | 2 | 2 | 2 | |||
| 73 | Prepare/submit final customer report | 3 | 6 | 10 | 6 | |||
| 74 | Audit against contractual deliverables | 3 | 5 | 8 | 5 | |||
| 75 | Obtain final customer approval | 2 | 3 | 4 | 3 | |||
| 76 | Internal | |||||||
| 77 | Hold lessons learned meeting | 1 | 1 | 1 | 1 | |||
| 78 | Update final internal report | 4 | 6 | 12 | 7 | |||
| 79 | Hold project team celebration event | 1 | 1 | 2 | 1 | |||
| Expected Project Finish Time: | Total Critical Path Variance: | days | ||||||
| days | ||||||||
| Total Critical Path Standard Deviation: | days | |||||||
| Probability of finishing the project in | 287 | days is | ||||||
| or | ||||||||
| % | ||||||||
| Probability of finishing the project in | 273 | days is | ||||||
| or | ||||||||
| % |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock