Question: Given the data below using SPT sequencing rule, which of the following statements is true? Job Processing time (in days) Due date (in days) 1

Given the data below using SPT sequencing rule, which of the following statements is true?

Job Processing time (in days) Due date (in days)
1 5 7
2 2 12
3 3 10
4 8 14

A. The average tardiness is 1.75.

B. The average number of jobs in the system is 2.5 days.

C. The batch of jobs will finish in 14 days.

D. The average flow time is 10.5 days.

Given the data below using SPT sequencing rule, which of the following

Given the data below using SPT sequencing rule, which of the following statements is true? A. The average tardiness is 1.75 . B. The average number of jobs in the system is 2.5 days. C. The batch of jobs will finish in 14 days. D. The average flow time is 10.5 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!