Question: Given the data below using SPT sequencing rule, which of the following statements is true? Job Processing time (in days) Due date (in days) 1
Given the data below using SPT sequencing rule, which of the following statements is true?
| Job | Processing time (in days) | Due date (in days) |
| 1 | 5 | 7 |
| 2 | 2 | 12 |
| 3 | 3 | 10 |
| 4 | 8 | 14 |
A. The average tardiness is 1.75.
B. The average number of jobs in the system is 2.5 days.
C. The batch of jobs will finish in 14 days.
D. The average flow time is 10.5 days.

Given the data below using SPT sequencing rule, which of the following statements is true? A. The average tardiness is 1.75 . B. The average number of jobs in the system is 2.5 days. C. The batch of jobs will finish in 14 days. D. The average flow time is 10.5 days
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts