Question: Given the Double S-curve below, what can be said about the SPI in March if the project had planned to complete 500 story points by
Given the Double S-curve below, what can be said about the SPI in March if the project had planned to complete 500 story points by the end of March?
Question 9 options: The SPI is exactly 1 The SPI is less than 1 The SPI is greater than 1 It is not possible to determine SPI from the information provided